Polished Concrete Cost Calculator
Price a polished-concrete job by grit pass — set a production rate per grit for the total labour hours, days, and direct cost per m² or sqft.
Estimate Polished Concrete Labour Hours & Cost
Polished concrete is priced completely differently from an epoxy coating. There is no material to spread across a coverage rate — the job is a sequence of grinding and polishing passes, each at a different diamond grit running at its own production rate. This calculator works the way the trade does: pick a finish, set a production rate (m²/hr or sqft/hr) for each grit pass, and it totals the labour hours and days for the job. Add your crew's hourly rate and any densifier, guard and consumables to turn those hours into a direct cost per m² or sqft — the baseline you build your price on top of.
Job Size
The floor area, how many grinders run in parallel, and how many people are on the job. More machines shorten the schedule; crew size drives the labour cost.
Finish
Pick a finish to load its typical pass sequence. Higher-gloss finishes add resin polishing grits, so they take more passes and more hours.
Pass Sequence & Production Rate
Each grit runs at its own rate (sqft/hr). Higher grits are usually faster. Edit any rate, switch a pass to cross-hatch (doubles its time), or add and remove grits to match the floor.
Costing (optional)
Add your crew's hourly rate to turn the hours into a labour cost, plus any densifier, guard and consumables as a lump sum. Leave blank to get hours only.
Enter your floor area above to see the estimated labour hours. Add a labour rate to turn the hours into a direct cost.
This is your direct cost — labour hours plus any materials you enter. Add mobilisation, overhead allocation, and your target margin on top to set the price you charge. Running polished-concrete jobs regularly? The Pro polished concrete estimator prices the whole job with your business overhead, profit and tax, and saves it as a client quote.
How the Polished Concrete Cost Calculator Works
- Choose your area unit (m² or sqft) and enter the floor area, plus how many grinders you'll run in parallel
- Pick a finish — Grind & Seal, Honed/Satin, Polished, or High-Gloss — to load its typical pass sequence
- Set a production rate for each grit pass (area per hour). Metal grinding passes default to 250 and resin polishing passes to 450 — flat starting points you edit to match your machines and the slab
- Switch any pass to cross-hatch (two directions) where you double back — it doubles that pass's time. Add or remove grits to match the finish you're actually running
- Optionally enter your fully-loaded hourly labour rate and a lump sum for materials and consumables (densifier, guard, diamond wear)
- Read off the total labour hours, the schedule in days, and your direct cost per m² or sqft
- Add mobilisation, overhead allocation, and your target margin on top to reach the price you charge
Examples
Frequently Asked Questions
Why price polished concrete by grit pass instead of by area?
Because there is almost no material cost to price — a polished floor is the concrete you already have, refined. The cost is labour: the hours your crew and machines spend grinding and polishing. And those hours are not one number per floor; each grit pass moves across the whole floor at its own speed. A 40-grit metal cut on a rough slab is slow; an 800-grit resin polish is fast. Adding the passes up (area ÷ rate for each) is the only honest way to get the hours, which is why this calculator is built around the pass sequence rather than a single "coverage rate".
What production rates should I use for each grit?
The rates loaded when you pick a finish are a starting guide, not fixed numbers — polished-concrete production varies enormously with the machine (a large planetary covers far more per hour than a single-head), the slab hardness, the number of heads, and the operator. As a rough guide, initial metal-bond cuts run slower (the machine is doing the most work), and resin polishing grits climb faster as the surface refines. The honest way to get your real rates is to time your crew across a representative area on one job and divide area by hours for each pass. Edit every rate here to match what your machines actually do.
What does cross-hatch (two directions) mean?
On the coarser grinding passes many contractors run the machine in one direction, then again at 90° to it, to make sure the whole surface is cut evenly and to remove the scratch pattern from the previous grit. That second direction roughly doubles the time for that pass. Switch a pass to "2 (cross-hatch)" here and the calculator doubles its hours. Finer resin polishing passes are usually run in a single direction, so leave those at one pass unless your process differs.
Does running more machines make the job cheaper?
No — it makes it faster, not cheaper. Two grinders finish the floor in roughly half the days, but they burn the same total operator-hours (in fact slightly more, because you're paying two operators). That's why this calculator uses machines only to work out the schedule in days, while the labour cost stays tied to the total operator-hours. More machines help you hit a deadline or reduce mobilisation days, not shrink the labour bill.
What's included in the cost — and what's left out?
The calculator gives you a direct cost: labour hours × your rate, plus any materials and consumables you enter as a lump sum (densifier, guard/sealer, diamond and resin pad wear). It deliberately leaves out mobilisation, overhead (insurance, vehicle, software, admin), and profit margin, because those vary too much between businesses to bake into a shared tool. The correct workflow is: use this to get a clean direct cost, add a fair share of your overhead, then apply your target margin — the Profit Margin Calculator handles that last step. The Pro polished concrete estimator does the whole roll-up (overhead, profit and tax) automatically and saves it as a client quote.
How do the finish levels differ?
Grind & Seal is the fastest and cheapest — a few metal grinding passes, densifier, and a sealer, for a matte-to-low-sheen ground look. Honed/Satin adds resin polishing to around 400 grit for a smooth, low-reflection finish. Polished (around 800 grit) carries the resin ladder further for a semi-gloss, more reflective floor. High-Gloss runs the full resin ladder to 1500–3000 grit and often a burnish pass for a mirror finish. Each step up adds passes, so it adds hours and cost on the same floor — which is exactly what the pass sequence here shows you.
Is this calculator for contractors or homeowners?
It's built for contractors pricing their own work, so the output is a direct cost, not a retail price. If you're a homeowner researching what a polished floor should cost, treat the direct cost here as roughly the labour-and-materials floor a contractor starts from — the quoted price you receive will add their overhead and margin on top, which is normal and correct. Published all-in polished-concrete prices vary widely by finish level, slab condition, and region, so use this to understand where the number comes from rather than as a quote.
How accurate are the hours?
As accurate as your production rates. The formula is exact (area × directions ÷ rate for each pass), so the hours are only as good as the rate you put in for each grit. A 20% error in a rate moves that pass's hours by 20%. The single best thing you can do is replace the seeded guide rates with numbers timed from your own crew on a real floor. The "override" field also lets you drop in a total hours figure from experience and cost from that instead of the passes.
Important Notes
- Polished concrete is a labour process, not a material one — the cost is the hours across each grit pass, so accurate production rates matter more than anything else
- The seeded rates are a starting guide — time your own crew on a real floor and edit every rate to match your machines and the slab
- Cross-hatch (two directions) doubles a pass's time — use it on the coarse grinding passes you run both ways, leave fine resin passes at one pass
- More machines shorten the schedule (days), not the labour cost — the operator-hours are the same
- This is a direct cost only — add mobilisation, overhead allocation, and your target margin to reach the price you charge
- For a full client quote with your overhead, profit and tax rolled in automatically, use the Pro polished concrete estimator